Board Update - July 2023

The Board approved the recommendation to delegate authority to the Superintendent or Her Designee regarding actions required to evaluate, negotiate, and award a selected vendor for Request for Qualification (RFQ) #23B-04-600 for the Purchase of Program Management Services for Renovation, Modernization, Addition, Expansion and New construction projects related to the Irving ISD 2023 Bond Program.  

Tentative Construction Timelines:

o   September 2024 – February 2026 (~18 months)

  • Replacement of Barton Elementary School

o   September 2024 – May 2026 (~21 months)

  • Replacement of Farine Elementary School

o   August 2024 – December 2025 (~17 months)

  • Replacement of Crockett Middle School

o   August 2025 – February 2027 (~18-20 months)

  • The Construction of a New Career and Technical Education Center

o   June 2024 – August 2025 (~12-15 months)

  • Replacement of Student Transportation and Logistics Center

o   April 2024 – June 2025 (~15 months)

  • Construction of one of the two New Baby Universities